“埃铁”全记录‖古老的国度 崭新的传奇——埃及斋月十日城铁路项目大事记(中英文)

A new achievement in an ancient civilization——milestones of the 10th of Ramadan Railway Project


▲2014年

12月24日,在埃及总统塞西的见证下,中国中铁—中航国际联合体与埃及交通部签署斋月十日城铁路项目的合作框架协议。

On December 24, 2014, in the presence of Egyptian President Abdel Fattah El-Sisi, the CREC-AVIC INTL Consortium and the Department of Transport of Egypt signed the cooperation framework agreement for the 10th of Ramadan Railway Project.

▲2015年

埃铁项目被纳入首批中埃产能合作优先项目清单。

In 2015, the 10th of Ramadan Railway Project was included in the first list of China-Egypt priority projects for production capacity cooperation.

▲2016年

1月21日,中国中铁—中航国际联合体与埃及国家隧道局签署《埃及斋月十日城铁路项目EPC合同》。项目合同金额为15亿美元(约折合人民币98.82亿元),合同工期为30个月。

On January 21, 2016, the CREC-AVIC INTL Consortium and the National Authority for Tunnels (NAT) of Egypt signed the EPC Contract for the 10th of Ramadan Railway Project in Egypt. The contract price reached 1.5 billion U.S. dollars (about 9.882 billion yuan), and the duration 30 months.

11月14日,深圳地铁与中国中铁—中航国际联合体签订斋月十日城市郊铁路运营维护与沿线综合开发联合体框架协议。

On November 14, 2016, Shenzhen Metro and CREC-AVIC INTL Consortium signed the Framework Agreement on Operation and Maintenance of and Integrated Development along the 10th of Ramadan Railway.

埃铁项目框架协议签约现场

▲2017年

8月15日,中国中铁—中航国际联合体和埃及国家隧道局签署埃铁项目商务合同。

On August 15, 2017, CREC-AVIC INTL Consortium and NAT signed the commercial contract for the 10th of Ramadan Railway Project.

▲2018年

12月3日,中车四方股份公司与中国中铁—中航国际联合体签署埃铁项目车辆供货合同,包括22列(132辆)市域动车组及12年维保服务。

On December 3, 2018, CRRC Qingdao Sifang Co., Ltd. (“CRRC Sifang” for short) and Chinese CREC-AVIC INTL Consortium signed the vehicle supply contract for the 10th of Ramadan Railway Project, including 22 intercity EMUs (132 cars) and 12-year maintenance service.

▲2019年

1月16日,中国进出口银行与埃及国家隧道局在开罗签署埃铁项目贷款协议,协议总金额12.39亿美元。

On January 16, 2019, the Export-Import Bank of China and NAT signed the loan contract worth 1.239 billion U.S. dollars for the 10th of Ramadan Railway Project in Cairo.

▲2020年

6月1日,埃铁项目轨道车辆正式开工。

On June 1, 2020, the production of rolling stock started.

10月24日,首座桥梁Suez桥完成架梁。

On October 24, 2020, the girder erection was completed on the first bridge, Suez Bridge.

11月22日,首座明挖隧道Badr Tunnel完成最后一节段混凝土顶板浇筑。

On November 22, 2020, the concrete pour for the roof slab of the last section of the first open-cut tunnel, Badr Tunnel, was completed.

11月23日,中国中铁—中航国际联合体与埃及国家隧道局签署备忘录(MOU)协议,以执行埃铁项目二期、三期工程。

On November 23, 2020, CREC-AVIC INTL Consortium and NAT signed a memorandum of understanding on the implementation of the Phase-II and Phase-III of the 10th of Ramadan Railway Project.

12月17日,第一批通信信号设备从中国发货运往开罗。

On December 17, 2020, the first batch of signaling and communication equipment was shipped from China to Cairo.

▲2021年

1月11日,轨道铺设正式启动。

On January 11, 2021, track laying started.

1月17日,Suez桥最后一个盖梁浇筑完成。

On January 17, 2021, the concrete pour for the last bent cap of the Suez Bridge was completed.

3月18日,深铁国际与中国中铁—中航国际联合体正式签订《埃及斋月十日城市郊铁路项目动车调试和综合联调服务合同》。

On March 18, 2021, Shenzhen Metro and CREC-AVIC INTL Consortium signed the EMU Commission and Integrated Test Service Contract for the 10th of Ramadan Railway Project in Egypt.

5月28日,中车四方股份公司为埃铁项目研制的首列市域电动车组在青岛下线。

On May 28, 2021, the first intercity EMU developed by CRRC Sifang for the 10th of Ramadan Railway rolled off the production line in Qingdao.

6月,首批次车辆段工艺设备顺利抵达埃及施工现场。

In June 2021, the first batch of rolling stock section process equipment arrived at the construction site in Egypt.

7月9日,接触网首根钢柱完成立杆作业。

On July 9, 2021, the first steel column for the catenary was erected.

8月31日,首批两台220kV牵引变压器顺利抵达埃及,9月13日直送2号牵引变电所,9月16日完成吊装。

On August 31, 2021, the first two 220kV traction transformers arrived in Egypt and were directly sent to the 2# traction substation on September 13 and hoisted on September 16.

9月5日,首批次电扶梯抵达埃及。

On September 5, 2021, the first batch of escalators arrived in Egypt.

9月7日,埃及总统塞西亲自为首批运抵埃及的斋月十日城铁路市域电动车组揭幕并登车参观。

On September 7, 2021, Egyptian President Abdel Fattah El-Sisi inaugurated the first batch of EMUs for the 10th of Ramadan Railway arriving in Egypt and boarded them for an inspection.

9月22日,首台扶梯在Badr车站开始吊装,9月26日完成机械安装。

On September 22, 2021, hoisting of the first escalator began at Badr Station, and mechanical installation was completed on September 26.

10月4日,首批供电交直流设备空运到施工现场。

On October 4, 2021, the first batch of AC and DC power supplies were transported to the construction site by air.

▲2022年

1月12日,A5段区间启动冷滑测试。

On January 12, 2022, the cold-running test was launched in Section A5.

1月13日,2号牵引变电所220kV成功受电。

On January 13, 2022, the 2# traction substation received power supply at 220kV.

3月28日,首列轻轨列车由A段阿德利·曼苏尔(Adly Mansour)站始发后,顺利抵达B段终点站新行政首都2站(Arts And Culture City)站台,标志着埃铁项目AB段顺利通车。

On March 28, 2022, the first light rail train departed from Adly Mansour Station, the starting station of Section A, and arrived at Arts and Culture City Station, the terminal of Section B, marking the official opening of Sections A and B.

4月30日,A3区段顺利完成列车逐级提速试验,最高瞬时速度达125km/h。

On April 30, 2022, the step-by-step speed-up test of the train was successfully completed in Section A3, with the highest instantaneous speed reaching 125 km/h.

7月3日,斋月十日城铁路通车试运行。

On July 3, 2022, the 10th of Ramadan Railway was opened for trial operation.